Green Energy Project Schedule
Task Name | Start | Finish |
ECM-1 Lighting | Thu 8/6/20 | Wed 8/12/20 |
ECM-2 HVAC & Controls, SC | Mon 11/11/19 | Tue 1/21/20 |
ECM-3 Building Envelope, | Mon 4/27/20 | Wed 4/29/20 |
ECM-3 Building Envelope, Window Film | Fri 9/6/19 | Mon 9/9/19 |
ECM-4, Water Conservation | Tue 3/31/20 | Thu 4/2/20 |
ECM-5, Transformers -3 | Sat 1/18/20 | Sat 1/18/20 |
ECM-6 PV Solar, RMDT 64 kWdc | Thu 4/16/20 | Thu 4/30/20 |
Anticipated Annual Energy Savings: $23,203