DPS Headquarters

DPS Headquarters
4491 Cerrillos Road

Green Energy Project Schedule

Task Name Start Finish
ECM-1 Lighting Mon 8/3/20 Wed 8/5/20
ECM-2 HVAC & Controls, Clean HX Mon 4/6/20 Fri 4/10/20
ECM-2 HVAC & Controls, Mon 11/11/19 Tue 1/21/20
ECM-3 Building Envelope, Mon 4/27/20 Thu 4/30/20
ECM-4, Water Conservation Mon 3/30/20 Wed 4/1/20
ECM-5, Transformers -3 Sat 1/18/20 Sat 2/29/20
ECM-6 PV Solar, RM 174.2 kWdc Mon 1/13/20 Wed 2/12/20

 

Anticipated Annual Energy Savings: $48,449