| Task Name |
Start |
Finish |
| ECM-1 Lighting |
Thu 8/13/20 |
Thu 8/27/20 |
| ECM-2 HVAC & Controls, Initiate Variable Primary HW/CHW |
Mon 12/2/19 |
Tue 1/21/20 |
| ECM-2 HVAC & Controls, |
Mon 11/11/19 |
Tue 1/21/20 |
| ECM-2 HVAC & Controls, Replace Boilers (2), Demo (3) |
Mon 8/26/19 |
Tue 10/15/19 |
| ECM-2 HVAC & Controls, Chiller Replacement |
Mon 8/26/19 |
Tue 10/15/19 |
| ECM-2 HVAC & Controls, VFD's |
Mon 2/10/20 |
Wed 2/12/20 |
| ECM-3 Building Envelope, |
Mon 4/27/20 |
Fri 5/1/20 |
| ECM-4, Water Conservation |
Thu 4/2/20 |
Tue 4/7/20 |
| ECM-6 PV Solar, RM 116.9 kWdc |
Mon 2/17/20 |
Fri 2/21/20 |
| Motor Vehicle Department Field Office |
Wed 3/18/20 |
Wed 9/2/20 |